Task 1: Performance Parameters

  1. Local conditions (e.g., weather, soiling, temperature, windspeed, irradiance)
  2. Site conditions (e.g., shading, orientation, utility voltage and frequency)
  3. Equipment and performance (e.g., system losses, inverter compatibility, inverter voltage [AC and DC])
  4. IV curve characteristics (e.g., short circuit, open circuit, maximum power point [MPP])
  5. Battery voltage
  6. Battery state of charge (SOC)

Task 2: System Monitoring Equipment and Applications

  1. Monitoring methods (e.g., app- and web-based, on-site)
  2. Data acquisition and control (e.g., DAS, SCADA)
  3. Instrumentation transformers (e.g., current transformers [CT], potential transformer [PT])
  4. Revenue grade meter
  5. Weather monitoring systems (e.g., albedometer, pyranometer, anemometer, thermometer)
  6. Battery temperature sensors
  7. Amp hour meter

Task 3: Electrical Test Equipment and Application

  1. Multimeters (e.g., current, voltage, resistance, continuity)
  2. Insulation testing devices (e.g., megohmmeter)
  3. IV curve tracer
  4. Infrared thermometer
  5. Irradiance meter
  6. Battery capacity testing devices (e.g., load tester)
  7. Hydrometer
  8. Refractometer
  9. Thermal camera

Task 4: Deviations from Expected Performance

  1. Test conditions (e.g., Standard Test Conditions [STC], nominal operating cell temperature [NOCT])
  2. Installation deficiencies
  3. Electrical faults (e.g., arc fault, ground fault)
  4. Production losses and their causes (e.g., weather, pollution, shading, animals, soiling, system degradation)
  5. System curtailment (e.g., export limitation, load control)

Task 5: Maintenance of PV Systems

  1. Scopes of work (e.g., preventative and reactive maintenance, inspections, cleaning, vegetation management, remote monitoring)
  2. Record keeping (e.g., system logging, data sheets, user manuals, as-built plan set, maintenance plan, photography)
  3. Visual inspection
  4. Equipment replacement (e.g., installation practices, lockout/tagout, service life)
  5. Equipment-specific maintenance requirements (e.g., lockout/tagout, torque requirements, cleaning)

Task 6: System Commissioning

  1. Visual inspection (e.g., Quality Assurance Quality Control [QAQC], installation checklists)
  2. Testing (e.g., thermography, string voltage, polarity)
  3. Proper operation of equipment (e.g., inverter operation, monitoring/communication, disconnects)
  4. Documentation (e.g., commissioning forms, manufacturer checklists, photo checklists, permission to operate [PTO])